15 January 2018 - 1 June 2018
% complete
16 January 2018 - 19 January 2018
% complete
Planning formalia and specification. Determine preliminary research questions and start discussions about what is the priority functionality for the client.
21 January 2018 - 16 February 2018
% complete
Literature study, check techniques, self study, report writing.
18 February 2018 - 27 April 2018
% complete
Mainly development but also some time for writing the method as well as formulating possible questionnaire and interview questions for user studies
2 April 2018 - 6 April 2018
% complete
Pilot study to make sure everything is working as expected
16 April 2018 - 20 April 2018
% complete
User studies at Gröna Lund including preparations
23 April 2018 - 21 May 2018
% complete
Focus on wrting report for submission. If there is time, improvements on the app are made based on user studies.
21 May 2018 - 3 June 2018