Ayodeji Fasore

ICH - 2018 Products Timeline

2018 ICH Product Development Timelines - High Level

High Level timelines for products to be developed in ICH for the calender year 2018

ICH - Product Development Timelines: January - August

15 January 2018 - 21 December 2018

This timeline shows the overall estimated product journey for 9Pay, Vyrus, CliqMi & 360 Awoof

9Pay

9Pay Product Development Activities

9Pay Commercialisation - 4 Weeks

Approx. 16 January 2018 - Approx. Feb 16, 2018

9Pay Commercialisation, Integrations, Test Runs & Development
- Airtime Testing & Provisioning
- Setting Up Test Environment
- Integrating with external Billers & Merchants
- Growth hacking & Marketing

Vyrus

Vyrus Product Development Timeline

MODI Product Development - 7 Weeks

Approx. Jan 17, 2018 - Approx. Mar 9, 2018

MODI Product Development Activities

Product Initialisation Activities

Jan 18, 2018 - Jan 26, 2018
  • Product Brief
  • Use Case Development
  • Process Flow & Data Diagrams
  • Wireframes & Prototypes

Product Development

Jan 29, 2018 - Feb 16, 2018
  • Front End Development
  • Back End Development
  • Code Review

Alpha Testing & External Integrations

Feb 19, 2018 - Feb 23, 2018
  • Unit Testing
  • System Integration Testing
  • User Acceptance Testing
  • Integrations with Payment Partners/Billers

Beta Testing & Live Migrations

Feb 26, 2018 - Mar 2, 2018
  • Migrating to Live Server
  • External Testing & Test Communities

Product Launch & Commercialization

Mar 5, 2018 - Mar 9, 2018
  • Product Launch
  • Post Launch Activities
  • Marketing & Growth Hacking Initialisation

CliqMI

CliqMi Product Development Timeline

CliqMi Product Development - 8 Weeks

Approx. Jan 29, 2018 - Approx. Feb 23, 2018

Product Development Process & Activities for CliqMi

360Awoof

360Awoof Product Development Timeline

360 Awoof Product Development - 16 Weeks

Approx. May 7, 2018 - Approx. Aug 24, 2018

Product Development Process & Activities for 360 Awoof