Term Project

Events

Sprint 1

10 Jan 2018 - 31 Jan 2018

Prepare Development Environment

17 Jan 2018 - 19 Jan 2018

Setup Cloud
Setup Database

Define Project Requirements

17 Jan 2018 - 21 Jan 2018

Meet with customers
Identify users
Define project constraints

*Software Development Plan

17 Jan 2018 - 29 Jan 2018

Define Input/Output

21 Jan 2018 - 26 Jan 2018

Create list of possible inputs
Define what output to give to user based on account type

Define Epics

31 Jan 2018 - 14 Feb 2018

Determine user experience based on access
Determine priority of epics
Security features of website
Separate epics/stories between GUI, database, scripts

Sprint 2

31 Jan 2018 - 19 Feb 2018

*First Draft of Project Backlog

5 Feb 2018 - 14 Feb 2018

Diagram Architecture

14 Feb 2018 - 21 Feb 2018

*Second Draft of Project Backlog

19 Feb 2018 - 5 Mar 2018

Sprint 3

19 Feb 2018 - 7 Mar 2018

Implement GUI

5 Mar 2018 - 19 Mar 2018

Implement login page
implement user class-based table display
Connect GUI to database model

Sprint 4

7 Mar 2018 - 2 Apr 2018

*Preliminary GUI

10 Mar 2018 - 28 Mar 2018

*Final Code Implementation

28 Mar 2018 - 18 Apr 2018

Testing Project

1 Apr 2018 - 18 Apr 2018

Sprint 5

2 Apr 2018 - 23 Apr 2018