Infrastructure Projects

Events

Domain Migration Prep

November 2017 - December 1 2017

Email Migration - Prep

November 2017 - December 1 2017

Domain Migration - Azure Testing

December 2017 - January 1 2018

Domain Migration - New Domain Setup

December 2017 - January 1 2018

Cloud File Server - Preparation

Dec 2017 - Jan 1 2018

Email Migration - Testing

January 2018 - Feb 1 2018

Email Migration - Cutover

Feb 2018 - Mar 1 2018

Cloud File Server - Cutover

February 2018 - April 2018

Domain Migration - Base infrastructure

March 2018 - April 1 2018

Computer Imaging - Prep

March 2018 - April 1 2018

Computer Imaging - Image New Hardware

May 2018 - Jun 1 2018

Domain Migration - Remaining Infrastructure

Jun 2018 - August 2018

Computer Imaging - End User Migration

jun 2018 - July 1 2018