Timeline Copy

1. Data

Status update catch up

11/19/2012 - 12/14/2012

2. Data

Pensioner reconciliation

11/19/2012 - 12/31/2012

3. Data

DC Unit reconciliation

11/20/2012 - 12/31/2012

4. Data

Solve off system members

12/28/2012 - 01/31/2013

5. Calcs

Calculation sign off

11/16/2012 - 11/30/2012

6. Calcs

System calculation rework and testing

11/30/2012 - 03/31/2013

7. Interfaces

PA and PY Process spec

11/19/2012 - 01/15/2013

PA and PY and system testing

01/11/2013 - 02/28/2013

8. Switch

Test in UAT

03/04/2013 - 03/15/2013

Switch, redirection and first contribution processed in UAT

9. Switch

Blackout

03/21/2013 - 04/15/2013

10. Switch

Switch exisitng assets

03/22/2013 - 04/01/2013

11. Switch

System update switch

04/02/2013 - 04/10/2013

12. Switch

Bulk redirection

04/11/2013 - 04/12/2013

13. Conts

Contribution testing

02/18/2013 - 04/19/2013

14. Conts

Feb conts unitised

03/20/2013 - 03/21/2013

15. Conts

March conts received

04/02/2013 - 04/03/2013

16. Conts

March conts updated

04/12/2013 - 04/14/2013

17. Conts

March conts unitised

04/22/2013 - 04/23/2013

18. Comms

Switch communication

03/31/2013 - 04/30/2013

19. Comms

DC Statement

04/01/2013 - 05/31/2013

20. Comms

DB Statement

04/01/2013 - 05/31/2013

21. Comms

Ex DB new DC letter and SORP

04/01/2013 - 04/30/2013

22. Comms

DC Rule change and SORP letter

04/01/2013 - 04/30/2013

23. Comms

Web enrolment letter

04/29/2013 - 05/17/2013

To all new and existing DC members