FY18 CMoC Series Project Timeline

Input

Vision Setting

August 1, 2017 - September 30, 2017

Finalize vision by end of September

Date Selection

August 31, 2017 - September 30, 2017

Finalize date selection by end of September

Recruitment

Co-chair Recruitment

August 1, 2017 - September 30, 2017

Have co-chairs in place to coordinate kick-off by mid-october

Committee Recruitment

August 1, 2017 - October 15, 2017

Recruit until kick-off (and beyond if needed)

Kick-off

Internal Kickoff

October 4, 2017

Hold internal kick-off strategic planning once dates/vision set.

Individual Summit Kick-off

October 9, 2017 - November 3, 2017

Kick-off individual summits with committee

Planning

Planning period

October 9, 2017 - July 29, 2018

Execution

Series Execution Period

April 6, 2018 - July 29, 2018

Evaluation

Series Evaluation Period

July 30, 2018 - August 10, 2018

individual evaluation will occur after each summit