nBOS Phase 2 Sprint 0 - Plan

Phase 1

Sprint 10

3 July 2017 - 14 July 2017

Phase 2

Sprint 0

12 July 2017 - 25 July 2017

Sprint 1

Jul 26, 2017 - August 8, 2017

Communication of Burnup

Aug 9, 2017

Team

Review Definition of Done

12 July 2017 - July 12, 2017

Balance Teams

Jul 15, 2017 - July 15, 2017

Team names

Jul 16, 2017 - July 16, 2017

Review how we work / improvements from Phase 1

Jul 16, 2017 - July 16, 2017

Review Phase 2 reporting

Jul 17, 2017 - July 19, 2017

Sprint 1 Showcase

8 August 2017

Backlog

Product / Epic Walkthrough

12 July 2017 - July 12, 2017

Agree Product MVP

Jul 13, 2017 - July 14, 2017

Agree MVP for Features

Jul 13, 2017 - July 14, 2017

Story Elaboration

Jul 15, 2017 - July 22, 2017

Sprint 0 Go / No

19 July 2017

Identify Factory dependencies

Jul 22, 2017 - July 24, 2017

Story Estimation Sprint 1

Jul 23, 2017 - July 25, 2017

Sprint 1 Planning

Jul 26, 2017 - July 26, 2017

Backlog Estimation

Jul 26, 2017 - August 4, 2017

Sprint 1 Development

Jul 27, 2017 - August 8, 2017

Release Plan

Aug 5, 2017 - August 5, 2017

Design

Technical Spikes

Jul 15, 2017 - 21 July 2017

Design Workshops

Jul 15, 2017 - July 19, 2017

Design VTI on a Page

17 July 2017 - 25 July 2017

Define Testing Approach

Jul 17, 2017 - July 19, 2017

Define how we will manage Phase 1 Products in Phase 2

Jul 23, 2017 - July 24, 2017