NMS to vXML Projects - Happy Path

This is a combined view of Inbound HC Migration, Inbound LabCalls Project and Migration, and SWN Migration Milestones

InBound LabCalls NMS to vXML Project & Migration

Inbound LabCalls NMS to vXML Project & Migration

March 1, 2017 - June 15, 2017

Client Communication begins

March 27, 2017

To meet with May by March 27

Dev Complete

March 31, 2017

ljkjghjgjjh

Deploy to PreProd and DBA review complete - QA Begins

Approx. April 3, 2017

QA/UAT Complete

April 14, 2017

QA = 4/3 through 4/14
UAT = 4/12 through 4/14

Deploy to SWN

Approx. April 19, 2017

LabCalls 8YY Migration Timeframe (All Customers)

April 24, 2017 - May 10, 2017

Mayo Test Timeframe

April 24, 2017 - April 26, 2017

Mayo Migration/Validation Timeframe

Approx. May 3, 2017 - Approx. May 10, 2017

**Go NO Go Decision for Plan B

May 10, 2017

HC/ExTra Change Freeze - SWN

May 11, 2017 - May 29, 2017

SWN HC/Extra SWN Migration Weekend

May 19, 2017

SWN Drop Dead - ATL goes Dark

June 15, 2017

InBound HC NMS to vXML Migration

Inbound HC NMS to VXML Migration

March 2, 2017 - April 15, 2017

Deploy to ATL and DEN06

May 2, 2017