Activities during the Hardening phase
Activities during the Hardening phase
31 March 2017 - 10 April 2017
% complete
31 March 2017 - 24 April 2017
% complete
31 March 2017
% complete
No more planned scope to be committed after this point
3 April 2017 - 4 April 2017
% complete
Create release branch for SP01
Prepare environments for TC1, with upgraded and clean db.
3 April 2017 - 25 April 2017
% complete
Run and Analyze all the automated tests everyday
5 April 2017 - 1 day
% complete
5 April 2017 - 12 April 2017
% complete
Test Cycle # 1: Scope issue testing (Plain Environment - All issues retesting on supported browsers and environments)
5 April 2017 - 25 April 2017
% complete
Continuously triage findings and take the status updates.
10 April 2017
% complete
12 April 2017 - 17 April 2017
% complete
13 April 2017 - 14 April 2017
% complete
17 April 2017 - 21 April 2017
% complete
Test Cycle # 2 - Execution on Upgrade Environment (12c)
- Regression Tests
- Online Help
18 April 2017 - 1 day
% complete
18 April 2017 - 19 April 2017
% complete
21 April 2017
% complete
Final Code Freeze - No more commits after this date, EOB Stavanger.
24 April 2017 - 24 April 2017
% complete
25 April 2017 - 26 April 2017
% complete
27 April 2017
% complete
27 April 2017
% complete
28 April 2017
% complete