Degree Works Application Implementation

Main

Project Starts

10/04/2012

Current week end

04/05/2013

Est. Project Close Date

09/06/2013

Initiation

Leadership Approved

10/03/2012

Initial Meeting

10/09/2012

Planning

Project Charter Approved

10/23/2012

Determine Add'l Consulting Requirements

11/06/2012

Execute Contract

11/16/2012 - 12/20/2012

Thanksgiving Holiday

11/22/2012 - 11/25/2012

Focus Call

12/04/2012

Winter Holiday Break

12/22/2012 - 01/01/2013

Implementation Launch

02/01/2013

Design

Installation Test - Remote

12/19/2012 - 12/26/2012

UG Scribing - Current Catalog

02/25/2013 - 04/12/2013

GR Scribing - Current Catalog

03/18/2013 - 04/19/2013

UG Scribing - Back Catalog

05/20/2013 - 06/07/2013

GR Scribing - Back Catalog

05/27/2013 - 06/07/2013

Build

Kick-off (on-site_

04/02/2013 - 04/03/2013

Grad Finale Week

04/15/2013 - 04/20/2013

Training 1 (on-site)

04/30/2013 - 05/02/2013

Single-sign on (Onsite)

05/07/2013 - 05/09/2013

Commencement Week Blackout

05/12/2013 - 05/18/2013

Training 2 (on-site)

06/04/2013 - 06/06/2013

Web Localization Training (Remote)

06/17/2013 - 06/21/2013

Training 3 (onsite)

07/09/2013 - 07/11/2013

Test

Formal Testing Phase

06/24/2013 - 07/05/2013

Target Launch Date

07/15/2013

Fall Start of School - Blackout

08/16/2013 - 09/07/2013

Transition

Help Desk Escalation Documentation & Transition Completed

10/11/2013

Operational Documentation Completed

10/11/2013

Lessons Learned Survey Review

10/11/2013

Close