Scope dashboard: https://jira.ec.tieto.com/secure/Dashboard.jspa?selectPageId=32462
End of business SVG - 17:00
February 13, 2017 - February 23, 2017
% complete
Release and User Documentation
February 13, 2017 - 2 days
% complete
Prepare TC1, TC1 backup and Bug Quest environment
February 15, 2017 - February 15, 2017
% complete
February 15, 2017 - February 17, 2017
% complete
Test Execution Plan : www.jira.tieto.com
Testing: Issues (ECPTs), relevant regression (PROD+FRMW)
February 18, 2017
% complete
Test Cycle 1 Code Freeze
February 20, 2017 - February 21, 2017
% complete
Release Candidate 1
Check CVS commits
Environment preparation for TC2
February 22, 2017 - February 24, 2017
% complete
Test Execution Plan : www.jira.tieto.com
Testing: re-test failed/fixed issues, critical regression test, UAT/Exploratory
February 24, 2017
% complete
End of Stavanger time
February 27, 2017 - March 5, 2017
% complete
February 27, 2017 - February 28, 2017
% complete
Prepare RC2 for Alpha testing
March 1, 2017 - March 2, 2017
% complete
March 1, 2017 - March 1, 2017
% complete
Test the installation, and basic functionality
March 2, 2017
% complete
March 6, 2017
% complete