Phase 1: Discovery

10/01/2012

Phase 2: The Roadmap

01/07/2013

Taking the feedback from the Discovery Phase and planning out a roadmap.

Phase 3: Paving the Road

03/14/2013

Implementing the plan approved in Phase 2: The Roadmap

FY12-13 Ends

05/31/2013

Initiation

Campus Diversity Council Retreat

09/21/2012

Planning

Project Plan Approved

10/17/2012

Create Planning Team

01/11/2013

Update IT Division on Progress

03/15/2013

Create Task Based Teams

03/18/2013 - 03/22/2013

Design

Create Survey

10/22/2012 - 11/16/2012

Review & Analyze Survey Response Themes & Ideas

01/14/2013 - 02/14/2013

Plan Activity Details

03/25/2013 - 04/05/2013

IT Leadership Approve Activities

04/08/2013

Build/Test

Survey Open for Completion

11/26/2012 - 12/07/2012

Create Roadmap Draft

02/15/2013

Roadmap Approved by IT Leadership

02/22/2013

Campus Diversity Council Spring Retreat

03/22/2013

Execute/Implement Activities

04/09/2013 - 05/24/2013

Transition

Present Summary of Themes

12/10/2012 - 12/21/2012

Prioritize What Can be done by May 31

03/08/2013

Assess Roadmap Progress

05/27/2013 - 05/30/2013

Close

Make Recommendations for FY13-14

05/31/2013