SoNHP Data Management System

Initiation

Phase 1: Vendor Selection

09/03/2012

Project Start Date

09/19/2012

Phase 2: Product Implementation

10/26/2012

Planning

Distribute RFP

09/24/2012

Design

Build

Receive RFP Questions

09/24/2012 - 10/01/2012

RFP Responses Received

10/03/2012

RFP Responses Due Date

10/12/2012

Test

Proof of Concept

10/04/2012 - 10/19/2012

Review Vendor Proposals

10/22/2012 - 10/23/2012

Transition

Vendor Selection Decision

10/24/2012

Close

Release to Implementation

10/25/2012