05 October 2012 - 19 October 2012
% complete
Estimate period for design stage.
19 October 2012 - 26 October 2012
% complete
Typically feedback occurs during the design stage and towards the end.
26 October 2012 - 02 November 2012
% complete
Digitising scheme design ready for submission.
02 November 2012 - 09 November 2012
% complete
Planning Submission and Registration
09 November 2012 - 04 January 2013
% complete
Determination period with Local Council
04 January 2013 - 25 January 2013
% complete
Production of Building Regulation Information by structural engineer and Ecotecture
25 January 2013 - 22 February 2013
% complete
22 February 2013 - 01 March 2013
% complete
01 March 2013 - 08 March 2013
% complete
Negotiation between Contractor Client and Architect
08 March 2013 - 05 April 2013
% complete
This is a typical lead in time we have provided for estimation purposes
05 April 2013 - 28 June 2013
% complete
New extension structural alterations and works to first floor phase
28 June 2013 - 23 August 2013
% complete
Interior fit out at ground floor including rewiring and replumbing