Tollgate Cottages, Crawley Down

Ecotecture QS Structural engineer and Contractors Timeline

Scheme design and survey 2 Weeks

05 October 2012 - 19 October 2012

Estimate period for design stage.

Feedback from client 1 Week

19 October 2012 - 26 October 2012

Typically feedback occurs during the design stage and towards the end.

Scheme onto computer 1 Week

26 October 2012 - 02 November 2012

Digitising scheme design ready for submission.

Planning submission 1 Week

02 November 2012 - 09 November 2012

Planning Submission and Registration

Planning determination 2 Months

09 November 2012 - 04 January 2013

Determination period with Local Council

Building regulations 3 Weeks

04 January 2013 - 25 January 2013

Production of Building Regulation Information by structural engineer and Ecotecture

Issue to tender 1 Month

25 January 2013 - 22 February 2013

Tender analysis 1 Week

22 February 2013 - 01 March 2013

Tender negotiation 1 Week

01 March 2013 - 08 March 2013

Negotiation between Contractor Client and Architect

Contractors lead in 1 Month

08 March 2013 - 05 April 2013

This is a typical lead in time we have provided for estimation purposes

Construction Phase 1 3 Months

05 April 2013 - 28 June 2013

New extension structural alterations and works to first floor phase

Construction Phase 2 2 Months

28 June 2013 - 23 August 2013

Interior fit out at ground floor including rewiring and replumbing