Peter Rock

Events

Adopção do Open-Source

Approx. 1 July 2016 - Approx. 31 December 2017

Desenho da GPlatform

Approx. 1 July 2016 - Approx. 15 August 2016

Desenvolvimento GPlatform

Approx. 16 August 2016 - Approx. 31 December 2017

Otimização do processo de Instalação

Approx. 1 November 2016 - Approx. 28 February 2017

Preparar Aplicações para a Cloud

Approx. 1 December 2016 - Approx. 30 April 2017

Integração Tekever

Approx. 1 January 2017 - Approx. 31 December 2017