Wireless Replacement Project G0-G3

G0-G2 Activities

G0-G2 Activities

31 May 2018 - 13 July 2018

ITF Build and Test

31 May 2018 - 11 June 2018

Wireless Network Design

12 June 2018 - 27 June 2018

Defenition of New Hal Standard for Wireless AP

26 June 2018 - 29 June 2018

First of type Deployment of a MARS stand

28 June 2018 - 11 July 2018

G3 Activities

G3 Documenation

19 June 2018 - 13 August 2018