Oleochemical timeline

Events

Overview

Project Planning

July 4, 2016 - November 1, 2016

Project Bid

November 10, 2016 - November 16, 2016

Identify Investor

November 16, 2016 - November 30, 2016

Permit Acquisition

Approx. December 1, 2016 - Approx. May 10, 2017

Construction & Operating Phase

Construction

May 20, 2017 - May 20, 2019

Operation (70%)

Approx. June 15, 2019 - Approx. June 15, 2020