06 September 2012 - 18 October 2012
% complete
Typical time frame for Ecotecture to start works
18 October 2012 - 25 October 2012
% complete
Surveying documents will provide the basis for all design work
25 October 2012 - 22 November 2012
% complete
These will be in the form of hand drawn sketches and basic 3d models
22 November 2012 - 06 December 2012
% complete
Dependant on work load of local planning office
06 December 2012 - 20 December 2012
% complete
AutoCAD digital floorplans elevations and site plans
20 December 2012 - 27 December 2012
% complete
Design and access statements and sustainability and planning statements
27 December 2012 - 03 January 2013
% complete
Uploaded via the planning portal Ecotecture will pay the planning fees and forward the cost for the application to you as part of our stage end invoice
03 January 2013 - 28 February 2013
% complete
This period can be elongated if the application is called into committee by the planner or local councillor
28 February 2013 - 28 March 2013
% complete
Client must appoint building control inspector Ecotecture to discharge of pre-commencement conditions
28 March 2013 - 11 April 2013
% complete
Structural engineer will issue a sketch scheme for the structural
04/11/2013
% complete
11 April 2013 - 09 May 2013
% complete
We would recommend a maximum of four highly recommended contractors we would typically recommend two or three of these four
09 May 2013 - 16 May 2013
% complete
To help make sense of the different tender figures accounting for differences between the pricing approach of individual contractors
16 May 2013 - 23 May 2013
% complete
Should the project be slightly over budget this is a good time to discuss and negotiate with your preferred contractor clever ways to bring costs down
23 May 2013 - 10 October 2013
% complete
The contract period would be provided by the contractor as part of the tender process we have given an estimate of how long this may take