Field Doc Project

Main

Field Doc Review Project

3/14/2010 - 9/30/2010

Overall Project Timeline

Final Guide Review

03/19/2010 - 04/15/2010

TSR/FSR Ref Update to Red/Green Matrix

03/29/2010 - 05/30/2010

Set mtg. w/ J. Tiefel, J. Becknell, J. Kochevar, B. Evans, J. Plew, T. Moffitt, G. Hanchar, M. Mala, M. Sall

Retire Documents

04/05/2010 - 07/31/2010

Prioritize Review of Documents- Categorize and Assign

04/06/2010 - 04/15/2010

Update Guide- remove & add b4 publishing

Add new COC label

04/5/2010 - 04/30/2010

Delete sect. to be put into Quality Docs

04/15/2010 - 04/30/2010

Parts

Meet w/ NSC to discuss retiring docs

04/5/2010 - 04/28/2010

Update Parts Policy

04/15/2010 - 05/01/2010

NERP

Review NERP Docs

06/15/2010 - 08/26/2010

Update documents

06/20/2010 - 07/15/2010

Retire NERP docs

07/15/2010 - 08/30/2010

Job Descriptions

Meet w/ Jay Britton on Job Description plan

04/10/2010 - 04/15/2010