My Extended Project

Events

Complete timeline and rationale

January 8, 2016 - 01/22/16

They have to be finished by this date

Confirm project ideas with group

January 8, 2016 - January 15, 2016

Within this time, I hope to have a final idea of the project and know where to start

Mentor & Group Meetings - Assign Tasks

January 13, 2016

Everyone should be clear on what they have to do

Workspace Needed

01/24/16 - 06/17/16

There is no rush for this, as long as it is sorted ready for the summer

Drone Components (Initial Research)

02/26/16 - 03/11/16

I plan to have researched all the components and know roughly what I am going to order

EXAM REVISION

March 18, 2016 - April 4, 2016

No EP during this time

Drone Components - Write up & Order

04/15/16 - 04/22/16

This needs to be written up before the exam period

EXAM PERIOD

April 22, 2016 - June 17, 2016

No EP during this time

Mid-Term Review

06/17/16 - 06/18/16

Complete the section of the PPR

Electronics (Initial Research)

06/22/16 - 07/18/16

All electronics research needs to be done before I do my soldering and PCB research

Soldering and PCB Research

07/18/16 - 07/19/16

I plan to have finished researching and to have made both PCBs at this point

Soldering Practice

07/20/16 - August 11, 2016

I plan to solder the final thing today, so I need to have finished practicing

HOLIDAY

July 27, 2016 - August 3, 2016

No EP

Solder the lighting circuit

August 11, 2016

All remaining research write up & Source evaluation

August 11, 2016 - August 13, 2016

HOLIDAY

August 15, 2016 - August 29, 2016

Drone Assembly & Marketplace

September 6, 2016 - September 9, 2016

Commentary write up

September 12, 2016 - September 14, 2016

Testing & Troubleshooting

September 15, 2016 - September 25, 2016

Evaluation & Filling Gaps

September 26, 2016 - October 3, 2016

HAND IN DATE

October 3, 2016