90 Harlands Road

Ecotecture QS Structural engineer and Contractors Timeline

Lead in time 6 Weeks

25 August 2012 - 06 October 2012

Survey existing structure 2 Weeks

06 October 2012 - 20 October 2012

Hand drawn sketches and scheme design 3 Weeks

20 October 2012 - 10 November 2012

Pre application advice from planning department 2 Weeks

10 November 2012 - 24 November 2012

Feedback from planning incorporated into scheme 1 Week

24 November 2012 - 01 December 2012

Scheme onto computer 1 Week

01 December 2012 - 08 December 2012

Planning submission 1 Week

08 December 2012 - 15 December 2012

Planning Submission and Registration

Planning determination 2 Months

15 December 2012 - 09 February 2013

Determination period with Local Council

Building regulations 3 Weeks

09 February 2013 - 02 March 2013

Production of Building Regulation Information by structural engineer and Ecotecture

Issue to tender 1 Month

02 March 2013 - 30 March 2013

Tender analysis 1 Week

30 March 2013 - 06 April 2013

Tender negotiation 1 Week

06 April 2013 - 13 April 2013

Negotiation between Contractor Client and Architect

Contractors lead in 1 Month

13 April 2013 - 11 May 2013

This is a typical lead in time we have provided for estimation purposes

Construction Phase 1 3 Months

11 May 2013 - 03 August 2013

Ground works super structure and weather proofing of extension including additional services if required

Construction Phase 2 3 Months

03 August 2013 - 26 October 2013

Knocking through first and second fix Internal finishes