Meadow Cottage

Main

Ecotecture QS Structural engineer and Contractors Timeline

Lead in time 6 Weeks

25 July 2012 - 05 September 2012

Survey existing structure 3 Weeks

05 September 2012 - 26 September 2012

Hand drawn sketches and scheme design 3 Weeks

26 September 2012 - 17 October 2012

Pre application advice from planning department 2 Weeks

17 October 2012 - 31 October 2012

Feedback from planning incorporated into scheme 1 Week

31 October 2012 - 07 November 2012

Scheme onto computer 1 Week

07 November 2012 - 14 November 2012

Planning submission 1 Week

14 November 2012 - 21 November 2012

Planning Submission and Registration

Planning determination 2 Months

21 November 2012 - 16 January 2013

Determination period with Local Council

Building regulations 2 Weeks

16 January 2013 - 30 January 2013

Production of Building Regulation Information by structural engineer and Ecotecture

Issue to tender 1 Month

30 January 2013 - 27 February 2013

Tender analysis 1 Week

27 February 2013 - 06 March 2013

Tender negotiation 1 Week

06 March 2013 - 13 March 2013

Negotiation between Contractor Client and Architect

Contractors lead in 1 Month

13 March 2013 - 10 April 2013

This is a typical lead in time we have provided for estimation purposes

Construction Phase 1 2 Months

10 April 2013 - 05 June 2013

Structural alterations carried out to form new layout within existing footprint improvement of insulation levels and replacement of existing windows where appropriate

Construction Phase 2 2 Months

05 June 2013 - 31 July 2013

Interior fit out finishes kitchen units and appliances