25 July 2012 - 05 September 2012
% complete
05 September 2012 - 26 September 2012
% complete
26 September 2012 - 17 October 2012
% complete
17 October 2012 - 31 October 2012
% complete
31 October 2012 - 07 November 2012
% complete
07 November 2012 - 14 November 2012
% complete
14 November 2012 - 21 November 2012
% complete
Planning Submission and Registration
21 November 2012 - 16 January 2013
% complete
Determination period with Local Council
16 January 2013 - 30 January 2013
% complete
Production of Building Regulation Information by structural engineer and Ecotecture
30 January 2013 - 27 February 2013
% complete
27 February 2013 - 06 March 2013
% complete
06 March 2013 - 13 March 2013
% complete
Negotiation between Contractor Client and Architect
13 March 2013 - 10 April 2013
% complete
This is a typical lead in time we have provided for estimation purposes
10 April 2013 - 05 June 2013
% complete
Structural alterations carried out to form new layout within existing footprint improvement of insulation levels and replacement of existing windows where appropriate
05 June 2013 - 31 July 2013
% complete
Interior fit out finishes kitchen units and appliances