NIIT We Can Messaging & Ad Design

Events

V1 Messaging Creation

August 11, 2016 - August 17, 2016

V1 Messaging Internal Review + Edits

August 17, 2016 - August 18, 2016

V1 Messaging Delivery/NIIT Review (Select 1 Headline + CTA. Move forward as is or request revision tweaks to selected option.)

August 19, 2016 - August 22, 2016

V2 Messaging Revisions (If Needed)

August 22, 2016 - August 23, 2016

V2 Messaging Final NIIT Review/Final Selection

August 24, 2016 - August 25, 2016

V1 (Above Escalator Display) Design Phase (3 Options)

August 26, 2016 - September 2, 2016

V1 (Above Escalator Display) Delivery/NIIT Review (Select 1 design option as is or request revision tweaks to selected option.)

September 2, 2016 - September 5, 2016

V2 (Above Escalator Display) Revision Phase

September 6, 2016 - September 8, 2016

V2 (Above Escalator Display) Final NIIT Review/Final Approval

September 8, 2016 - September 9, 2016

(Diorama) Design (Created promptly based on the chosen layout/look and feel of the "Escalator Display")

September 12, 2016

(Diorama) NIIT minor revision requests

September 12, 2016 - September 13, 2016

Finalize, Prep & Handoff final "Above Escalator" & "Diorama" files for print.

September 14, 2016