-
Use Cases
-
Resources
-
Pricing
25 June 2012 - 02 July 2012
% complete
Typical time frame for Ecotecture to start works
02 July 2012 - 09 July 2012
% complete
Surveying documents will provide the basis for all design work
09 July 2012 - 23 July 2012
% complete
These will be in the form of hand drawn sketches and basic 3d models
07/23/2012
% complete
23 July 2012 - 06 August 2012
% complete
Dependant on work load of local planning office
06 August 2012 - 20 August 2012
% complete
Dependant on feedback from case officer
20 August 2012 - 03 September 2012
% complete
AutoCAD digital floorplans elevations and site plans
03 September 2012 - 10 September 2012
% complete
Design and access statements and sustainability and planning statements
10 September 2012 - 17 September 2012
% complete
Uploaded via the planning portal Ecotecture will pay the planning fees and forward the cost for the application to you as part of our stage end invoice
17 September 2012 - 12 November 2012
% complete
This period can be elongated if the application is called into committee by the planner or local councillor
12 November 2012 - 10 December 2012
% complete
Client must appoint building control inspector Ecotecture to discharge of pre-commencement conditions
10 December 2012 - 24 December 2012
% complete
Structural engineer will issue a sketch scheme for the structural
24 December 2012 - 07 January 2013
% complete
This gives the design team an opportunity to iron out any items before issuing to the contractor
07 January 2013 - 04 February 2013
% complete
We would recommend a maximum of four highly recommended contractors we would typically recommend two or three of these four
04 February 2013 - 11 February 2013
% complete
To help make sense of the different tender figures accounting for differences between the pricing approach of individual contractors
11 February 2013 - 18 February 2013
% complete
Should the project be slightly over budget this is a good time to discuss and negotiate with your preferred contractor clever ways to bring costs down
18 February 2013 - 02 September 2013
% complete
The contract period would be provided by the contractor as part of the tender process we have given an estimate of how long this may take
02 September 2013
% complete
Target moving in date
02 September 2013 - 17 February 2014
% complete
Snagging periods vary from 3 to 12 months based on complexity of the project this can be defined at the start of the contract period within the contract documentation