01 June 2012 - 13 July 2012
% complete
13 July 2012 - 03 August 2012
% complete
03 August 2012 - 24 August 2012
% complete
24 August 2012 - 07 September 2012
% complete
07 September 2012 - 14 September 2012
% complete
14 September 2012 - 21 September 2012
% complete
21 September 2012 - 28 September 2012
% complete
Planning Submission and Registration
28 September 2012 - 23 November 2012
% complete
Determination period with Local Council
23 November 2012 - 07 December 2012
% complete
Production of Building Regulation Information by structural engineer and Ecotecture
11/23/2012
% complete
07 December 2012 - 04 January 2013
% complete
04 January 2013 - 11 January 2013
% complete
11 January 2013 - 18 January 2013
% complete
Negotiation between Contractor Client and Architect
18 January 2013 - 15 February 2013
% complete
This is a typical lead in time we have provided for estimation purposes
15 February 2013 - 10 May 2013
% complete
Ground works super structure and weather proofing of extension including additional services if required
10 May 2013 - 05 July 2013
% complete
Knocking through into the existing ground and first floor Internal finishes