1 Meadowlands

Ecotecture QS Structural engineer and Contractors Timeline

Lead in time 6 Weeks

01 June 2012 - 13 July 2012

Survey existing structure 3 Weeks

13 July 2012 - 03 August 2012

Hand drawn sketches and scheme design 3 Weeks

03 August 2012 - 24 August 2012

Pre application advice from planning department 2 Weeks

24 August 2012 - 07 September 2012

Feedback from planning incorporated into scheme 1 Week

07 September 2012 - 14 September 2012

Scheme onto computer 1 Week

14 September 2012 - 21 September 2012

Planning submission 1 Week

21 September 2012 - 28 September 2012

Planning Submission and Registration

Planning determination 2 Months

28 September 2012 - 23 November 2012

Determination period with Local Council

Building regulations 2 Weeks

23 November 2012 - 07 December 2012

Production of Building Regulation Information by structural engineer and Ecotecture

Extent of current fee proposal

11/23/2012

Issue to tender 1 Month

07 December 2012 - 04 January 2013

Tender analysis 1 Week

04 January 2013 - 11 January 2013

Tender negotiation 1 Week

11 January 2013 - 18 January 2013

Negotiation between Contractor Client and Architect

Contractors lead in 1 Month

18 January 2013 - 15 February 2013

This is a typical lead in time we have provided for estimation purposes

Construction Phase 1 3 Months

15 February 2013 - 10 May 2013

Ground works super structure and weather proofing of extension including additional services if required

Construction Phase 2 2 Months

10 May 2013 - 05 July 2013

Knocking through into the existing ground and first floor Internal finishes