Buick Final Four Project Timeline

Events

Kick off and Discovery

March 1, 2016

Kickoff Meeting

Dev R&D

March 2, 2016 - March 9, 2016

-R&D Capture and keying process
-Developing Underlying tech

Pre Production

March 2, 2016 - March 7, 2016
  • Story Boards
  • Voice Over Auditions
  • Floor Plan / User Flow

Pre Pro Review/Iterate/Signoff

March 7, 2016 - March 9, 2016
  • Review First round of story boards
  • Iterate on Story Boards
  • Client Sign Off on Story Boards
  • Client Sign Off on Voice Overs
  • Client Sign off on Floor Plan / User Flow

Production

March 9, 2016 - March 22, 2016

Once design sign off is complete
- Development of signup kiosk
- Photo Capture Kiosk
- Email Server

Production Review/Iteration/Signoff

March 22, 2016 - March 28, 2016

-Production review and iteration
-Final Production Signoff

Testing Q/A and Delivery

March 24, 2016 - April 1, 2016
  • Q/A Testing
  • Bug Reporting and Fixing
  • Wrap up
  • Delivery to site

Complete and Deliver

April 2, 2016

Final Build is ready and onsite at the event