NELSONS COTTAGE

Ecotecture timeline

Lead in time 6 Weeks

01 May 2012 - 12 June 2012

Hand drawn sketches and scheme design 3 Weeks

12 June 2012 - 03 July 2012

Pre application advice from planning department 2 Weeks

03 July 2012 - 17 July 2012

Feedback from planning incorporated into scheme 1 Week

17 July 2012 - 24 July 2012

Scheme onto computer 1 Week

24 July 2012 - 31 July 2012

Planning submission 1 Week

31 July 2012 - 07 August 2012

Planning Submission and Registration

Planning determination 2 Months

07 August 2012 - 02 October 2012

Determination period with Local Council

Building regulations application can be registered

10/01/2012

Building regulations 2 Weeks

02 October 2012 - 16 October 2012

Production of Building Regulation Information by structural engineer and Ecotecture

Issue to tender 1 Month

16 October 2012 - 13 November 2012

Tender analysis 1 Week

13 November 2012 - 20 November 2012

Tender negotiation 1 Week

20 November 2012 - 27 November 2012

Negotiation between Contractor Client and Architect

Contractors lead in 1 Month

27 November 2012 - 25 December 2012

This is a typical lead in time we have provided for estimation purposes

Construction Phase 1 3 Months

25 December 2012 - 19 March 2013

Ground works super structure and weather proofing of extension including additional services if required

Construction Phase 2 2 Months

19 March 2013 - 14 May 2013

Knocking through into the existing ground and first floor Internal finishes