City of Mississauga - Mississauga Valley Community Centre

Substantial Completion- June 17th

Events

Admin & Document Procurement

February 1, 2016 - February 29, 2016

Site Visits By Civil Contractor & DNA Mechanical

February 1, 2016 - February 28, 2016

Shop Drawings-Munters, Sheet Metal, Controls

February 1, 2016 - February 28, 2016

Controls

April 4, 2016 - June 17, 2016

TA Canada

Civil Work-Curbs, Bollards, Fencing, Coring

April 4, 2016 - April 29, 2016

Demolition-Electrical, Civil, DNA Mechanical

April 4, 2016 - April 18, 2016

Ice Out

April 4, 2016 - June 17, 2016

Electrical

April 4, 2016 - June 17, 2016

Demo Disconnect
Wire new Units

Indoor Construction Start date

April 4, 2016 - June 17, 2016

Sheet Metal Supply & Install

April 11, 2016 - May 6, 2016

Install Gas Piping -DNA Mechanical

April 18, 2016 - April 29, 2016

Supply & Install Insulation

May 9, 2016 - May 25, 2016

Munters Equipment Delivery

June 6, 2016 - June 10, 2016

Assumption March 7th-Shop drawing approval by engineer

Crane

June 6, 2016 - June 10, 2016

Munters Equipment Installation-DNA Mechanical

June 6, 2016 - June 10, 2016

Balancing

June 10, 2016

Start Up & Commissioning-DNA Mechanical

June 13, 2016

Deliver close out documentation Via Dropbox/Binders

June 17, 2016