Vesper Project Timeline (Copy)

Courtyards_Clubhouse

Design-Final Approval and Prelim Budgeting 2.5 wks

January 7, 2016 - January 25, 2016

CD Development - 2 wks

January 26, 2016 - February 8, 2016

GC Final Bidding/VE Finalization - 4 wks

February 8, 2016 - March 6, 2016

Permits - 6 wks (submit March 7)

March 6, 2016 - April 16, 2016

Procurement/Construction - 90 days

April 16, 2016 - July 14, 2016

Furniture Install

July 14, 2016 - August 1, 2016

University Plains_Model Unit

Final Design

February 10 2016 - March 15, 2016

Procurement/Construction

march 10 2016 - April 20, 2016

Furniture Install

April 20, 2016 - April 26, 2016

CLS Austin Office

Design

January 7, 2016 - January 14, 2016

Procurement/Construction

January 14, 2016 - February 17, 2016

Install/Completion

February 17, 2016 - February 23, 2016

The Ivy_Clubhouse

Procurement/Construction

January 7, 2016 - March 16, 2016

Furniture Installation

March 9 2016 - March 16 2016

Fountains_Clubhouse

Design - Final Approval and Prelim Budgeting - 2.5 wks

January 7, 2016 - January 25, 2016

CD Development - 2 wks

January 26 2016 - February 8, 2016

GC Final Bidding and VE/Finalization - 4 wks

February 8, 2016 - March 6, 2016

Permits - 7 wks (submit March 7)

March 14, 2016 - April 24, 2016

Procurement/Construction - 90 days

Apr 25, 2016 - July 23, 2016

Furniture Install

Jul 24, 2016 - July 30, 2016

Campus View_Clubhouse

Conceptual Design

January 7, 2016 - February 1, 2016

Design - Final Approval and Prelim Budgeting - 4 wks

February 1, 2016 - February 28, 2016

CD Development - 2 wks

February 28, 2016 - March 12, 2016

GC Budgeting and VE/Finalization - 2 wks

March 12, 2016 - April 8, 2016

Permit - 6 wks (submit April 11)

April 8, 2016 - May 19, 2016

Procurement/Construction - 90 days

May 19, 2016 - August 16, 2016

Furniture Installation

August 15 2016 - August 21 2016

Courtyards_Model Unit

FInal Design

January 7, 2016 - January 13, 2016

Procurement/Construction

January 13, 2016 - February 9, 2016

Furniture Install

February 9, 2016 - February 15, 2016

University Plains_Clubhouse

Conceptual Design

January 7, 2016 - February 1, 2016

Design - Final Approval and Prelim Budgeting - 4 wks

February 2, 2016 - February 29, 2016

CD Development - 2 wks

February 29, 2016 - March 13, 2016

GC Final Bidding and VE/Finalization - 2 wks

March 13, 2016 - April 9, 2016

Permit - 6 wks (submit April 11)

April 9, 2016 - May 20, 2016

Procurement/Construction - 90 days

May 20, 2016 - August 17, 2016

Furniture Install

August 15 2016 - August 21 2016

Campus View_Model Unit

Final Design

february 1 2016 - february 15 2016

Procurement

february 18 2016 - April 2, 2016

Furniture Insallation

April 2, 2016 - April 8, 2016

Thompson_Tanning Room

Design

January 7, 2016 - January 13, 2016

Procurement/Construction

January 13, 2016 - January 26, 2016

Install/Completion

January 26, 2016 - February 1, 2016