DYE Next Phases

Maple St & Main St Pilots

Device Decision

January 25, 2016 - February 10, 2016

for Main St Pilot

Device Decision

January 25, 2016 - February 10, 2016

Decide on devices for Maple St

Contract Execution

February 11, 2016 - March 18, 2016

Dependency: How long will it take to get devices to where we need them

Contract Execution

February 11, 2016 - March 18, 2016

UX

March 1, 2016 - May 31, 2016

UX

March 1, 2016 - May 31, 2016

Configure Devices

March 18, 2016 - April 21, 2016

Configure Devices

March 18, 2016 - April 21, 2016

Install Devices

April 22, 2016 - May 27, 2016

All 3 cities at the same time. Drea, Hanzel and I will spend 1 week in each city and train someone to do the rest so we can move on to USN.

Install Devices

April 22, 2016 - May 27, 2016

All 3 cities at the same time. Drea, Hanzel and I will spend 1 week in each city and train someone to do the rest so we can move on to USN.

Gather Data

May 9, 2016 - August 31, 2016

Gather Data

May 9, 2016 - August 31, 2016

DYE CAN GO-LIVE

September 1, 2016 - September 2, 2016

DYE USN GO-LIVE

September 1, 2016 - September 2, 2016

Experience live to customers

DYE LITE

Data Research

January 25, 2016 - February 12, 2016

No access to smart meter data. Researching other options.

UX Design

February 19, 2016 - May 13, 2016

Contract with G4C

February 19, 2016 - March 11, 2016

Inform algorithm

March 1, 2016 - May 31, 2016

Use data sources found to teach algorithm

LITE Product Complete

Approx. May 23, 2016 - May 31, 2016