Sustainability Report Example Timeline

Events

Project Kickoff

February 1, 2016 - February 5, 2016

Project timeline refined, meetings scheduled, assets provided to Domoto Brands, review of materiality assessment results.

Leadership Interviews (if needed)

February 8, 2016 - February 12, 2016

Leaderhship interviews (if needed). May be scheduled later than second week in February dependent of client schedule.

Discovery, Outline Refinement + Concept Development

February 8, 2016 - February 19, 2016

Design Concept and Exploration

February 22, 2016 - March 15, 2016

2015 Report Content Creation Draft 1

February 26, 2016 - March 15, 2016

Draft 1 Content Due to Prologis

March 15, 2016

Draft 1 Client Comments Due

March 18, 2016

Design Implementation

March 21, 2016 - May 3, 2016

2015 Report Content Creation Draft 2

March 21, 2016 - April 5, 2016

Draft 2 Content Due to Prologis

April 5, 2016

Draft 2 Client Comments Due

April 8, 2016

Comments from client with review from legal.

Report Content Draft 3

April 11, 2016 - April 22, 2016

Draft 3 Content Due to Prologis

April 22, 2016

Draft 3 Client Comments Due

April 26, 2016

Executive team comments due for final implemetation.

Final Draft Due

May 3, 2016

Submit to GRI

May 4, 2016

PDF Interactive Programming/Linking

May 16, 2016 - May 17, 2016

Final Report PDF Delivered

May 18, 2016

Report Launch on IMPACT Day

May 20, 2016