219 - 26 HOATHLY HILL (OPTION TWO)

Ecotecture QS Structural engineer and Contractors Timeline

Building regulations 1 Month

16 April 2012 - 14 May 2012

Production of Building Regulation Information by structural engineer and Ecotecture QS Schedule of Works

Issue to tender 1 Month

14 May 2012 - 11 June 2012

Tender analysis 1 Week

11 June 2012 - 18 June 2012

Tender negotiation 1 Week

18 June 2012 - 25 June 2012

Negotiation between Contractor Client and Architect

Contractors lead in 1 Month

25 June 2012 - 23 July 2012

This is a typical lead in time we have provided for estimation purposes

Construction Phase 1 4 Months

23 July 2012 - 11/12/2012

Ground works super structure and weather proofing of extension including additional services if required

Construction Phase 2 3.5 Months

03/01/2013 - 07 June 2013

Knocking through into the existing ground and first floor Insulation to loft New velux or sunpipes and new internal finishes