Vesper Project Timeline (Copy)

The Ivy_Clubhouse

Place Orders/Construction

January 7, 2016 - March 16, 2016

Install/Completion

Mar 17, 2016 - March 30, 2016

CLS Austin Office

Design

January 7, 2016 - January 14, 2016

Place Orders/Construction

Jan 15, 2016 - February 18, 2016

Install/Completion

Feb 19, 2016 - March 3, 2016

Events

Fountains_Clubhouse

University Plains_Clubhouse

University Plains_Model Unit

Campus View_Clubhouse

Campus View_Model Unit

Thompson_Tanning Room

Design

January 7, 2016 - January 13, 2016

Place Orders/Construction

Jan 14, 2016 - February 3, 2016

Install/Completion

Feb 4, 2016 - February 17, 2016

Courtyards_Model Unit

Design

January 7, 2016 - January 13, 2016

Place Orders/Construction

Jan 14, 2016 - February 10, 2016

Install/Completion

Feb 11, 2016 - February 24, 2016

Courtyards_Clubhouse

Design

January 7, 2016 - January 25, 2016

Adjustments

January 26, 2016 - February 8, 2016

Out for Bid

Feb 9, 2016 - February 22, 2016

Adjustments

Feb 23, 2016 - March 7, 2016

Permits

Mar 8, 2016 - April 1, 2016

Construction

Apr 2, 2016 - August 1, 2016