New Product Mass production schedule 2016

Belt Cable Twin Head

Kick-Off

November 5, 2015

Development

November 5, 2015 - February 5, 2016

CMF - lock down

November 10, 2015

Marketing name/color - lock down

November 10, 2015

SKU release

November 13, 2015

1st sample for Photo shoot

November 16, 2015

Packaging artwork release

December 14, 2015

PO release date to factory

December 18, 2015

Production 2k Qtys

Approx. January 20, 2016 - Approx. January 27, 2016

ETA HK warehouse

Approx. January 28, 2016 - Approx. January 29, 2016

Nautical Cable - Belt/Belt XL/Night/Key

Development

October 13, 2015 - March 11, 2016

1st sample for photo shoot

Approx. December 30, 2015

PO release date to Factory

January 7, 2016

Packaging artwork release

Approx. January 13, 2016

Sales & Show samples (~20pcs each SKU)

Approx. January 28, 2016 - Approx. January 29, 2016

Production (4 SKUs)

Approx. February 22, 2016 - Approx. March 4, 2016

ETA HK warehouse

Approx. March 7, 2016 - Approx. March 8, 2016