Unified Nantong Solar Rollout Plan

Events

Monitor electricity usage (Phase 1 buildings)

June 1, 2017 - August 31, 2017

30%

June 1, 2017

Phase 1 Install and Connect (1.25 MW)

September 1, 2017 - December 31, 2017

Monitor electricity usage (Phase 2 buildings)

January 1, 2018 - March 31, 2018

60%

January 1, 2018

Phase 2 Install and Connect (1.25 MW)

April 1, 2018 - July 31, 2018

Monitor electricity usage (Phase 3 buildings)

April 1, 2018 - June 30, 2018

100%

April 1, 2018

Phase 3 Install and Connect (2.5 MW)

July 1, 2018 - September 30, 2018