DPB 'Be able to act' Release Plan

Public Holidays

New Year's Day

January 1, 2016

Chinese New Year

February 8, 2016 - February 9, 2016

Good Friday

March 25, 2016

Iterations

I0

Approx. December 15, 2015 - Approx. January 6, 2016

I1

January 7, 2016 - January 20, 2016

I2

Jan 21, 2016 - February 3, 2016

I3

Feb 4, 2016 - February 17, 2016

I4

Feb 18, 2016 - March 2, 2016

I5

Mar 3, 2016 - March 16, 2016

I6

Mar 17, 2016 - March 30, 2016

I7

Mar 31, 2016 - April 13, 2016

I8

Apr 14, 2016 - April 27, 2016

RFP + Blockers

Dev Done

Approx. March 16, 2016

SIT Regresssion

March 17, 2016 - March 23, 2016

UAT & PenTest

Approx. Mar 24, 2016 - April 6, 2016

UAT Signoff

Approx. April 8, 2016

CAB

Approx. April 13, 2016

AppStore Upload

Approx. April 15, 2016

Backend GoLive (OOC)

Approx. April 15, 2016

App Live

Approx. April 29, 2016