Client Website Schedule Sample

Events

Responsive Wireframes (mobile, tablet, desktop)

Approx. November 25, 2015 - November 27, 2015

Wireframe Presentation

Approx. November 30, 2015 - November 30, 2015

Homepage Designs

Approx. December 1, 2015 - December 1, 2015

Homepage Design Presentation

Approx. December 2, 2015 - December 2, 2015

Homepage Design Revision 1

Approx. December 9, 2015 - December 9, 2015

Homepage Revision 1 Presentation

Approx. December 11, 2015 - December 11, 2015

Includes Dec 12/13 weekend

Homepage Design Revision 2

Approx. December 14, 2015 - December 14, 2015

Homepage Design Revision 2 (Final) Presentation

Approx. December 15, 2015 - December 15, 2015

Homepage Design Final

Approx. December 16, 2015 - December 16, 2015

Excludes 19/20 for the weekend

Homepage Website Coding

Approx. December 17, 2015 - December 27, 2015

Dec 25th is a holiday

Interior Pages Design

December 17, 2015 - December 23, 2015

Interior Pages Presentation

December 24, 2015

Not sure if GOCO minds meeting on the 24th, Christmas Eve

Interior Pages Design Revision 1

December 28, 2015 - December 31, 2015

Interior Pages Design Revision 1 Presentation

January 4, 2016

Interior Pages Design Revision 2

January 5, 2016 - January 7, 2016

Interior Page Designs Revision 2 (Final) Presentation

January 8, 2016

Interior Pages Final Design

January 11, 2016 - January 12, 2016

Interior Pages Website Coding

January 13, 2016 - January 29, 2016

Includes 2 weekends

Copy Writing (homepage new copy, all pages, meta title/description)

January 13, 2016 - January 29, 2016

Internal QC, Client QC, Edits, CMS

February 1, 2016 - February 10, 2016

Internal QC (2 days)
Client QC (2 days)
Revisions (3 days including weekend)

GO LIVE

February 14, 2016 - February 16, 2016

CMS Training/Project Completion and Handover

February 23, 2016