MSU Snowflake - Timeline

Pre-Production

Kick Off Meeting

November 2, 2015

Initial MSU Delivery

November 3, 2015 - November 4, 2015

MSU will deliver the following:

  • High level comps
  • Vector Icon and Background examples
  • Sticker Categories
  • Snowflake Flash example and source
  • Determine need for following accessibility requirement
  • Determination on whether # of icons will be limited to three

Wire Frames

November 5, 2015 - November 8, 2015

Pixo will deliver initial wireframes to client via Invision

MSU Review

November 9, 2015 - November 10, 2015

Design Mockups

November 10, 2015 - November 15, 2015

Deliver mockups to MSU via Invision

MSU Review

November 16, 2015 - November 17, 2015

Production

Programming

November 9, 2015 - December 3, 2015

QA Testing

November 24, 2015 - December 3, 2015

Website Handoff

December 1, 2015 - December 3, 2015

Work on handoff of website code to MSU. Configure any firewall or other configuration settings appropriately.

Launch MSU Snowflake Website

December 4, 2015