NCAA Signage: Design/Bid/Build

Construction Package 1

DD/CD - Package #1

November 1, 2015 - November 20, 2015

Construction - Package #1

November 30, 2015 - December 18, 2015

Construction Package 2: Signage

DD - Package #2

November 2, 2015 - November 27, 2015

CD Package #2

November 30, 2015 - January 8, 2016

Bidding

January 11, 2016 - February 5, 2016

Fabrication

February 8, 2016 - April 15, 2016

Installation- Package #2

April 18, 2016 - May 27, 2016

Construction

2016 Women's Final Four

April 2, 2016

Events