2-Way Communications

Design

Discovery

10/19/15 - 10/23/15

Deliver design document for 2-Way review

Discovery Signoff

10/26/2015 - 10/28/2015

2-Way feedback on design document back to Pixo and sign-off after changes are complete

Wireframes

10/29/15 - 11/11/15

Pixo to deliver wireframes for 2-Way review

Wireframe Signoff

11/12/15 - 11/19/15

2-Way feedback on wireframes back to Pixo and sign-off after changes are complete

UI Mockups

11/20/15 - 12/4/15

2-Way feedback on UI Mockups back to Pixo and sign-off after changes are complete

UI Mockup Signoff

12/7/15 - 12/11/15

2-Way feedback on UI mockup back to Pixo and sign-off after changes are complete

Development

Backend Development

10/29/15 - 11/19/15

Infrastructure, database and API development

App Development

11/20/15 - 1/15/16

Mobile app development
Feedback system development

User Testing

1/18/16 - 1/29/16

User testing with Diane's user group.

Apple Submission

1/29/16

Application submitted to Apple for approval