GEAEC

Manufacturing

GE9X FBO1 Fan Case Manufacturing (2 of 4 remaining)

September 9, 2015 - October 30, 2015

Hybrid Preform Development (W&W 3+2 and 4+1)

Approx. November 9, 2015 - Approx. February 26, 2016

FBO1B Fan Case Manufacturing (1-3 parts)

Approx. January 4, 2016 - Approx. March 18, 2016

FBO1.5 Fan Case Manufacturing

Approx. March 14, 2016 - Approx. November 23, 2016

Tooling

FBO1B Outer Segment Plating

September 21, 2015 - November 30, 2015

FBO1.5 Outer Segment Fabrication

September 21, 2015 - Approx. February 19, 2016