Jasper Square Redevelopment Project

Contract Items

Contract Negotiation

November 2, 2015 - December 1, 2015

Final Consultant Selection

November 2, 2015

RDC / Common Council Approval & Execution of Agreement

December 1, 2015 - January 15, 2016

Design Phase(s)

Preliminary Design / 30% Design

February 1, 2016 - February 29, 2016

60% Design

March 1, 2016 - April 29, 2016

90% Design

May 2, 2016 - June 30, 2016

Final Construction Documents for Phase 1

July 1, 2016 - August 31, 2016

Final Construction Documents - Phase 2

January 9, 2017 - February 28, 2017

Phase One Construction

Phase 1 Bidding

September 1, 2016 - September 29, 2016

Phase 1 Hardscape Construction

October 2, 2016 - March 31, 2017

Phase 1 Landscape Installation

April 3, 2017 - May 5, 2017

Phase Two Construction

Phase 2 Bidding

March 1, 2017 - March 31, 2017

Phase 2 Hardscape Construction

April 3, 2017 - June 30, 2017

Substantial Completion

Approx. July 15, 2017

Strassenfest

August 5, 2017

Phase 2 Landscape Installation

September 4, 2017 - October 31, 2017

Final Acceptance

Approx. November 15, 2017