Foundation Pad

Approx. August 3, 2015 - August 7, 2015

Jake Tackett J&M Excavation 817-689-8165

Foundation forms and trenching

August 10, 2015 - August 14, 2015

Sam Beharry

Plumbing rough installation

August 17, 2015 - August 21, 2015

Johnson Plumbing Co.

Foundation

August 24, 2015 - September 26, 2015

Retrench as necessary
Steel
Cables
Floor plugs
Inspections
Pour

Sam Beharry & Childress engineers (the foundation design engineer), Fargo Testing Lab (concrete QC testing)).

Durasol

October 6, 2015 - October 23, 2015

Framing

October 26, 2015 - November 20, 2015

Roof

Nov 21, 2015 - December 4, 2015

Insulation

Dec 5, 2015 - December 11, 2015

Today

Today - Present

Meetings

Meet with Tim (2:00)

August 1, 2015

Verified location of foundation pad, septic, metal building, and well. Monnet to provide Tim basic information about metal building (dimensions, desired services, etc.).

Meet with Tim

August 29, 2015