Frank Mckechnie Community Centre - HVAC Replacement Schedule

Frank McKechnie Project Timeline

The Van Mechanical Services Team
Shaun Marshall GM VMSI 416-881-5333
Deni DiTullio Principle 416-881-7333
Richard Price 416-881-5333
Jade Heaton 905-264-1229 ext 201

Bonding-Completed

May 12, 2015

Contract & Document Procurement-Completed

May 29, 2015

Mechanical Shop Drawing Distribution-Completed

June 1, 2015 - August 1, 2015

Mobilization & Site Measurements-Completed

8 October 2015 - 13 October 2015

Demolition-Completed

9 October 2015 - 13 October 2015

Crane Friday AM, Electrical Thursday Before EOD, Sheet Metal Thursday Afternoon or Friday AM.
Roofing Thursday/Friday Demo/Take Out old Curb, Place New One, Ben Welder- Weekend/Or Tuesday. Scrap bin confirmed load/leave with Triple.

Electrical-Outstanding

9 October 2015 - 23 November 2015

Our Electricians will have ERV, Boiler #1 &#2, Pump completed by November 16th.
The MUA & CU will be power up after the first portion is completed.

Ductwork-Completed

9 October 2015 - 23 October 2015

Roofing-Completed

9 October 2015 - 13 October 2015

Thursday take off
Friday/Tuesday complete work

Curb Delivery-Completed

9 October 2015

Engineered Air/HTS Curbs to be delivered

Crane Hoisting-Completed

9 October 2015 - 14 October 2015

Crane to Hoist Twice 9th & 14th.

Boiler Delivery-Completed

13 October 2015

Install Water Piping-Completed

13 October 2015 - 23 October 2015

Install P-1-Completed

13 October 2015 - 23 October 2015

P-1 Delivery-Completed

13 October 2015 - 14 October 2015

Faisal & Mark- Confirmed

Install Boiler-Completed

13 October 2015 - 23 October 2015

Controls-Outstanding

13 October 2015 - 27 November 2015

Confirmed with TA scope that is outstanding- Team is mobilizing to complete.

CU-1 Delivery-Completed

14 October 2015

Confirmed

ERV-1 Delivery Completed

14 October 2015

Confirmed

MUA-2 Delivery-Completed

14 October 2015

Confirmed

Install Refrigerant Piping- Outstanding

19 October 2015 - 23 October 2015

Confirm structural before proceeding.

Balancing-Outstanding

19 October 2015 - 27 November 2015

ABG Scheduled for week of 23rd

Install Gas Piping-Completed

20 October 2015 - October 30, 2015

Insulation-Outstanding

20 October 2015 - 27 November 2015

AD Scheduled for week of Nov 23rd

Start -Up & Commissioning-Outstanding

2 November 2015 - 18 November 2015

O&M Manuals Preperation & Delivery

9 November 2015 - 30 November 2015