timeline

Events

Project Report

June 20, 2015 - July 2, 2015

Prepartion and Drafting the detailed Project Report

Registraion as SSI

June 25, 2015 - June 28, 2015

Selection of Site

July 1, 2015 - July 31, 2015

Searching and Finalising the Location

Loan

July 6, 2015 - August 1, 2015

Machinery Procurement

July 31, 2015 - September 15, 2015

Visiting various vendor and finalising the machinries and delivery of the machine at the site

Recutement of Labor

September 15, 2015 - September 30, 2015

Trial Run and Production

September 28, 2015 - November 18, 2015