Parker Residence

Divisions

General Requirements

August 17, 2015 - August 31, 2015

Concrete

September 1, 2015 - October 31, 2015

Site Work

September 1, 2015 - September 30, 2015

Masonary

October 1, 2015 - November 30, 2015

Wood and Plastics

November 1, 2015 - December 31, 2015

Thermal & Moisture Protection

December 1, 2015 - January 31, 2016

Mechanical

January 1, 2016 - January 31, 2016

Electrical

January 1, 2016 - January 31, 2016

Special Construction

January 1, 2016 - January 31, 2016

Doors & Windows

January 1, 2016 - March 31, 2016

Finishes

February 1, 2016 - May 31, 2016

Specialties

April 1, 2016 - May 31, 2016

Masonary

April 1, 2016 - May 31, 2016

Special Construction

May 1, 2016 - May 31, 2016

Electrical

May 1, 2016 - May 31, 2016

Equipment

May 1, 2016 - May 31, 2016

Mechanical

May 1, 2016 - May 31, 2016