Brampton Chinguacousy Library - HVAC Control & PCN #1 Schedule

Events

Control Wiring Roughin (Electrical)

June 18, 2015 - June 19, 2015

Ceiling Prep Work

June 18, 2015

Motorized Damper Installation

June 19, 2015

Repair Insulation (Resulting from Motorized Damper Installation)

June 22, 2015

Control Wiring Termination (In Control Panel)

June 23, 2015 - June 24, 2015

Motorized Damper (Actuator Installation)

June 23, 2015

Commissioning

June 25, 2015

Equipment Start up

June 26, 2015