POE Timeline

Sberbank

Requirements

April 6, 2015 - April 24, 2015

Development

April 27, 2015 - May 29, 2015

QA Testing

June 1, 2015 - June 12, 2015

UAT Testing

June 15, 2015 - June 19, 2015

Go Live Prep

June 22, 2015 - July 3, 2015

Go Live

July 6, 2015 - July 10, 2015