PDSB Kingswood - Boiler Replacement - Team Schedule

Events

Admin & Documentation Procurement

May 18, 2015 - May 28, 2015

Mechanical Shop Drawings

May 18, 2015 - June 12, 2015

Site Orientation & Mobilzation

June 12, 2015 - June 15, 2015

Demotion (Electrical)

June 15, 2015 - June 19, 2015

Demolition (Controls)

June 15, 2015 - June 19, 2015

Demolition (Equipment & Piping)

June 15, 2015 - June 30, 2015

House Keeping Pads

June 29, 2015 - July 4, 2015

Burner Delivery

July 13, 2015

Boiler Installation

July 13, 2015 - July 14, 2015

Boiler Delivery

July 13, 2015

Boiler Piping Installation

July 13, 2015 - July 31, 2015

Pumps/Tanks/Separator Installation

July 13, 2015 - July 24, 2015

Burner Installation

July 15, 2015 - July 16, 2015

Pumps/Tanks/Separator Delivery

July 15, 2015

Controls

August 3, 2015 - August 31, 2015

Gas Piping Installation

August 3, 2015 - August 7, 2015

Insulation

August 4, 2015 - August 14, 2015

Electrical

August 4, 2015 - August 28, 2015

Roofing

August 6, 2015 - August 7, 2015

Venting Delivery

August 14, 2015

Venting Installation

August 17, 2015 - August 18, 2015

Chemical Treatment

August 24, 2015 - August 28, 2015

Commissioning

August 27, 2015 - August 28, 2015

Close Out Documentation

August 30, 2015