ECR - Dry Run

Events

Tim's Plan

May 8, 2015

Tim's schedule/plan for no-op testing

Communicate to Team

May 8, 2015

Complete IT Failover Plan

May 13, 2015

Mark to complete the schedule for failing services over to Las Vegas before Dry Run

Complete BCP Plan

May 13, 2015

What is BCP team's plan for the Dry Run

Provide Responses to Eng Leadership

May 13, 2015

Jason to respond to all questions:
1. Puppet'd machines
2. Push out of move
3. Plan for no-op push
4. Critical service list
5. Plan for BCP planning

Today

May 14, 2015

Communicate to All

May 15, 2015

Corp and Engineering

Place Orders for Support Hardware/Contractrs

May 15, 2015

Dry Run Rehearsal #1

May 18, 2015

Dry Run Rehearsal #2

May 25, 2015

Dry Run Rehearsal #3

June 1, 2015

Dry Run Rehearsal Final

June 8, 2015

Moratorium - Code Stabilization Allowed

06/11/2015 - 06/12/2015

Moratorium - Alternative Code Push Plan

06/13/2015 - 06/14/2015

Data Center Shutdown and Bringup

06/13/2015 - 06/14/2015